Kyushu Elec. to Halt Reactor Due to Antiterror Facility Delay

Kyushu Elec. to Halt Reactor Due to Antiterror Facility Delay

   Fukuoka, June 14 (Jiji Press)--Kyushu Electric Power Co. <9508> is seen halting a southwestern Japan nuclear reactor next March due to a delay in the construction of a facility to prepare for terrorist attacks.
   The No. 1 reactor at the Fukuoka-based company's Sendai power plant in Kagoshima Prefecture will be the first in Japan whose operation will be suspended because of a delay in the construction of such a facility, which would be used to ensure nuclear plant safety in the event of a terrorist attack.
   In April this year, the Nuclear Regulation Authority decided to order a halt to a nuclear reactor in operation if the construction of such a facility is not completed by the designated deadline.
   On Wednesday, the authority indicated its policy of issuing such an order about a week before the deadline.
   At Kyushu Electric, the construction of the facility for the 890,000-kilowatt reactor is unlikely to finish before the deadline of March 17, 2020.

To read a full story, please click here to find out how to subscribe.

NATION

Aomori Tourism Information

HEADLINES

POLITICS
Japan Govt Voices Concern over US Downing of Iranian Drone in Strait of Hormuz
ECONOMY
Japan Consumer Prices Up 0.6% in June, Smallest Rise in 2 Yrs
SPORTS
MLB: Tennis Star Naomi Osaka to Throw 1st Pitch before Dodgers-Angels Game Wed.
OTHER
European Embassies Offer Condolences over 33 Deaths in KyoAni Arson

Aomori Tourism Information

GOSHOGAWARA
Introduction of Tachineputa, Town of Kanagi and West Tsugaru Peninsula
・ GOSHOGAWARA 1
・ GOSHOGAWARA 2
・ GOSHOGAWARA 3
JOMON
An early culture with pottery
・ JOMON 1
・ JOMON 2
・ JOMON 3
・ JOMON 4

AFP-JIJI PRESS NEWS JOURNAL


Photos