Thailand’s three-airport high-speed rail project remains stalled as CP Group seeks to terminate its contract with the SRT over land handover, financing and BOI obstacles.
Thailand’s long-delayed high-speed rail project linking Don Mueang, Suvarnabhumi and U-Tapao airports faces a potential legal battle, with the CP Group-led private partner seeking to terminate its contract while the State Railway of Thailand (SRT) insists construction must begin.
The 220-kilometre railway, a flagship infrastructure project for the Eastern Economic Corridor (EEC), is designed to connect Bangkok with the EEC in less than 60 minutes, with trains reaching speeds of up to 250 kilometres per hour.
However, more than seven years after the contract was signed, construction has yet to begin.
The project has been plagued by disputes over land handover, a public watercourse, financing difficulties caused by the Covid-19 pandemic and unresolved investment promotion requirements.Seven years of delays
The SRT signed the public-private partnership agreement with the CP-led consortium on October 24, 2019. The project, subsequently undertaken by Asia Era One Co Ltd, involves an investment of 224.54 billion baht under a 50-year contract.
Originally scheduled to begin operations in 2024, the railway remains stalled.
Even before the contract was signed, negotiations over investment conditions took more than a year. Further disagreements emerged over the conditions for issuing the Notice to Proceed (NTP), which authorises construction to begin.Land handover becomes first major obstacle
One of the earliest disputes concerned the handover of construction land.
The private partner insisted that the SRT hand over 100% of the required land before construction could begin.
The SRT, however, maintained that the contract allowed the land to be handed over in stages, starting with 50%.
The disagreement delayed the NTP and prevented construction from getting under way.
Public waterway raises legal concerns
Another obstacle involved land around Bueng Suea Dam and a public watercourse in the Makkasan area.
Although the watercourse had long fallen into disuse and become heavily silted, making it no longer visible on the ground, it remained recorded on land title deeds. The private partner feared that accepting the NTP without resolving the issue could create legal complications and disrupt construction.
The SRT maintained that the disputed watercourse accounted for only about 1% of the project’s total construction area. It also consulted the Office of the Attorney General, which concluded that the public watercourse issue was not a condition for land handover.
Nevertheless, the issue added to the project’s prolonged delays.
Covid-19 triggers demands for revised payment terms
As land disputes continued, the Covid-19 pandemic introduced further financial uncertainty from 2020 onwards.
The collapse in air travel, uncertainty over future passenger revenue, changes in construction costs and interest rates undermined the financial assumptions used during the bidding process.
These developments made it increasingly difficult for the private partner to secure loans from financial institutions.
To ease the burden, the CP-led consortium proposed amending the investment contract, particularly the payment structure for government financial support of up to 149.65 billion baht.
Under the original agreement, government support would be paid after construction was completed.
The private partner instead proposed a “pay-as-you-build” arrangement, under which the government would release funds progressively as construction advanced. The proposal was intended to reduce upfront investment requirements and improve access to financing.
The consortium also sought changes to payment arrangements for the Airport Rail Link concession rights, including payment by instalments.
However, the proposed amendments required extensive negotiations to ensure that the government would not be disadvantaged. Any changes also required approval from the Eastern Economic Corridor Policy Committee and the Cabinet.
The negotiations dragged on without a resolution.
BOI obstacles lead to termination claim
Another critical issue involved investment promotion approval from the Board of Investment (BOI). Under the investment agreement, the private partner was required to obtain the necessary investment promotion approval before the NTP could be issued.
However, unresolved financing arrangements and continuing negotiations over contract amendments prevented the private partner from completing the supporting documentation for its BOI application.
The application eventually lapsed, creating another obstacle to construction.
Asia Era One subsequently asserted its contractual right to terminate the agreement, citing unresolved conditions relating to investment promotion and the NTP.
How the contract dispute escalated
The disagreement developed through several key stages:
July 6, 2026: Asia Era One formally notified the SRT that it was exercising its right to terminate the contract under Clause 6.2, citing problems involving investment promotion requirements and the NTP.
August 2026: The Transport Ministry disclosed that the company had submitted a second letter reaffirming its intention to terminate the agreement, despite the government’s request for the project to proceed.
October 14, 2026: The SRT issued an NTP instructing the private partner to begin construction, maintaining that it had fulfilled its contractual obligations. Asia Era One challenged the notice and reiterated its termination claim.
The SRT maintains that the contract remains binding and rejects the private partner’s grounds for termination. The conflicting positions have now pushed the project into a formal contractual dispute.
Legal action looms as November 28 deadline approaches
Under the contractual dispute resolution provisions, both parties have 60 days to negotiate a settlement, unless they agree on a different timeframe. If negotiations fail, either party may refer the dispute to a Thai court with the appropriate jurisdiction.
SRT Governor Anan Phonimdaeng confirmed that the current 60-day negotiation period is due to expire on November 28, 2026. If no agreement is reached by that date, the SRT will consult the Office of the Attorney General to determine how to proceed through the legal system.
The dispute leaves the future of one of Thailand’s most significant infrastructure projects uncertain, with construction yet to begin despite years of negotiations and investment commitments.
Source: Bangkokbiznews