While all 34 international airlines surveyed support moving their operations to Long Thanh International Airport in Dong Nai City, southern Vietnam, 24 plan to make the switch from late October 2027, while the remaining 10 propose doing so from summer 2028 or later.
Long Thanh International Airport is still targeting December 24 for the start of operations, but moving airlines from Tan Son Nhat International Airport in Ho Chi Minh City to the new facility is proving to be a complex process.
Many foreign carriers have proposed delaying the transition to allow sufficient time to adjust their operations and ensure service stability.
Foreign airlines seek phased transition to Long Thanh
A survey by the Civil Aviation Authority of Vietnam found that international airlines welcomed the new airport’s infrastructure and service capacity but called for an appropriate transition roadmap.
The airlines said relocating operations involves more than simply changing departure and arrival airports.
The process could take six to 12 months to adjust flight networks, aircraft and crew arrangements, staffing, ground services and ticketing systems.
Foreign aviation authorities may also need to conduct inspections and approve safety conditions before allowing airlines to operate at the new airport.
For example, to launch direct cargo services from Long Thanh to the United States, the U.S. Transportation Security Administration must conduct an on-site inspection and assessment of the airport.
International logistics companies such as UPS, FedEx, DHL and Cargolux also require coordinated facilities for express cargo terminals, customs clearance, truck handling and road connections.
Technical preparations and assessments for cargo operations could take around 12 months.
Airlines have also called for improvements to medical services, four-star or higher transit hotels and convenient transport links with Ho Chi Minh City.
Under the Airports Corporation of Vietnam’s plan, Vietnam Airlines is expected to operate 72 flights per week at the initial stage, while Vietjet could operate up to 294 weekly flights. Both figures cover domestic services only.
Long Thanh conducts 3-month trial as global airports offer lessons
The Long Thanh airport developer said its operational readiness program comprises 55 scenarios, to be conducted in three phases from September to December 2026.
However, Long Thanh will have only around three months for integrated trial operations, from late September until its planned commercial launch in late December 2026.
International experience shows that major airports often spend several months testing systems, conducting emergency drills and addressing problems before welcoming passengers.
Beijing Daxing International Airport in China, for example, began flight trials in May 2019 and conducted multiple exercises before officially opening on September 25 that year.
Its sixth trial involved 100 simulated flights, more than 13,000 passengers and 9,000 pieces of luggage.
At Istanbul Airport in Turkey, operational preparations began in May 2018, involving more than 100 scenarios and 63 days of testing.
The airport initially handled around eight to 10 flights per day, maintaining this real-world trial phase for about five months before completing the full transfer of operations in April 2019.
Similarly, Hong Kong International Airport conducted a series of operational drills starting in January 1998. Its final exercise involved around 12,000 people, 35 airlines and four aircraft ahead of its opening in July that year.
Notably, Terminal 1 at Incheon International Airport in South Korea needed around nine months to enter commercial operation after construction was completed, while Terminal 4 at Singapore’s Changi Airport required approximately 12 months.
These examples show that there is no fixed trial period applicable to every airport. However, multiple rounds of testing, fault detection, corrective work and retesting are essential to operational readiness.
Aviation experts said Long Thanh is a nationally significant aviation infrastructure project and that bringing it into operation early is important. However, the schedule must be balanced with operational quality and efficiency.
They said a phased approach, aligned with the readiness of airport infrastructure, airlines and supporting services, would help minimize disruption for passengers and businesses.
Spanning 5,000 hectares in Dong Nai City, Long Thanh International Airport is set to become Vietnam’s largest airport, with a total estimated investment of more than US$16 billion.
Developed in three phases, the airport is designed to handle up to 100 million passengers and five million tonnes of cargo annually upon full completion.
Its first phase, costing approximately VND109 trillion ($4.22 billion), will have an annual capacity of 25 million passengers and 1.2 million tonnes of cargo.
The airport is expected to ease pressure on Ho Chi Minh City’s Tan Son Nhat International Airport and become a major international aviation hub, while driving infrastructure, industrial, and urban development in the surrounding region.
Thanh Ha – Cong Trung / Tuoi Tre News