24 ERC show-cause orders issued to power firms over grid outages

MANILA BULLETIN

November 4, 2026

The Philippines’ power regulator ordered 13 generation companies to explain why their facilities suffered prolonged, unscheduled outages, intensifying scrutiny on energy providers following widespread grid disruptions and surging electricity costs in the country.
The Energy Regulatory Commission (ERC) issued 24 show-cause orders against the offending companies after investigations showed their generating units exceeded maximum allowable unplanned downtime limits set by government reliability rules.
The ERC push targets units and subsidiaries belonging to some of the country’s largest energy conglomerates.
Among those receiving show-cause orders are Bac-Man Geothermal Inc., Belgrove Power Corp., Central Azucarera De San Antonio Inc., Cleanergy 9 Power Inc., Energy Development Corp., Meridian Power Inc., Republic Cement & Building Materials Inc., SPC Island Power Corp., Sunwest Water & Electric Co. 2, Therma Mobile Inc., Therma Visayas Inc., and Toledo Power Co.
The affected entities include operations linked to major industry players Aboitiz Power Corp., Energy Development Corp., Meralco PowerGen Corp., and San Miguel Corp., as well as an energy firm associated with former Ako-Bicol party-list representative Zaldy Co.
The ERC order follows months of mounting public pressure over recurring electricity shortages and elevated utility bills that have disproportionately impacted consumers in Visayas and Mindanao.
The commission earlier launched preliminary assessments to evaluate plant performance, having issued non-compliance notices to 25 generation companies in June to gather operational data.
Under statutory limits formalised under Resolution No. 23 in July, generating assets are bound by strict caps on total unplanned offline days before operators face administrative remedies.
Conventional hydropower facilities operate under the tightest operational window, capped at 12.72 days of unplanned downtime per year. Run-of-river hydropower facilities are limited to 12.03 days, while pumped-storage hydro installations are allowed 18.98 days.
Geothermal facilities are permitted up to 22.98 days, diesel-powered plants receive 21.09 days, and gas turbines are capped at 26.92 days. Biomass generating units have a threshold of 32.06 days, while oil-fired thermal plants hold the longest allowance at 37.03 days before breaching performance standards.
The agency stated it will determine financial penalties once it evaluates formal responses submitted by the generators. Financial sanctions will be imposed if evaluations confirm that facilities breached statutory reliability standards.
Jiji Press