(Update) TEPCO Briefly Halts Fuel Loading at Kashiwazaki-Kariwa Reactor

(Update) TEPCO Briefly Halts Fuel Loading at Kashiwazaki-Kariwa Reactor

   Tokyo, April 17 (Jiji Press)--Tokyo Electric Power Company Holdings Inc. briefly halted fuel loading at the idled No. 7 reactor at its Kashiwazaki-Kariwa nuclear power plant in Niigata Prefecture, central Japan, on Wednesday following an electrical system problem.
   TEPCO said there are no safety concerns over the problem, and resumed the work at around 11:30 p.m. after replacing equipment.
   According to TEPCO, the breaker of a certain device was turned on around 7 a.m. to prepare to insert control rods, but it immediately shut off. The company is investigating the cause of the incident.
   A problem also occurred with related equipment on Monday night, and the fuel loading work was suspended for three hours.
   Since the work began on Monday afternoon, 41 of the 872 fuel assemblies have been transported into the No. 7 reactor. With control rods in place for all of the transported fuel assemblies, TEPCO said that there are no safety concerns.

To read a full story, please click here to find out how to subscribe.

NATION

HEADLINES

POLITICS
China's Xi to Visit France, Serbia, Hungary in 1st European Tour since Pandemic
ECONOMY
Japan March Housing Starts Down 12.8%, 10th Consecutive Monthly Fall
SPORTS
Soccer: PSG Clinches French Top League Title for 12th Time and 3rd Straight Year
OTHER
Vacant Houses across Japan as of Last Oct. Hit Record 9 Million: Govt Survey

AFP-JIJI PRESS NEWS JOURNAL


Photos