Tsuruga Nuclear Reactor Decommissioning Completion Postponed

Tsuruga Nuclear Reactor Decommissioning Completion Postponed

   Fukui, May 19 (Jiji Press)--Japan Atomic Power Co. said Monday that it has postponed the completion date of decommissioning work for the No. 1 reactor at its Tsuruga nuclear power plant in Fukui Prefecture, central Japan, to fiscal 2047 from fiscal 2040.
   The postponement came as additional work became necessary following a change of a contractor in charge of dismantling facilities in the reactor building.
   Japan Atomic Power reported the schedule change to the Fukui prefectural government and the Nuclear Regulation Authority.
   A decision was made in 2015 to decommission the reactor, which started operating in 1970.
   In 2021, a contractor that was expected to demolish large facilities around the reactor gave up its plan to win the order. Japan Atomic Power has selected a new contractor, which will take about seven more years to dismantle the facilities.

To read a full story, please click here to find out how to subscribe.

NATIONAL

HEADLINES

POLITICS
Opposition Parties Jointly Demand Agriculture Min. Eto Resign over Rice Gaffe
ECONOMY
Only 10% of Rice Released by Govt in March Has Become Available to Consumers
SPORTS
Soccer: Mitoma Becomes 1st Japanese to Score 10 Goals in a Season in England
OTHER
Veteran Enka Singer Yukio Hashi, 82, Diagnosed with Dementia of Alzheimer Type

AFP-JIJI PRESS NEWS JOURNAL


Photos